Parliament Faces 'Notre Dame-Style' Fire Risk as Restoration Costs Climb and MPs Delay Decisions

Every year of inaction adds an estimated £420m
The public accounts committee says delay is itself driving up the restoration bill for the Palace of Westminster.
Mark

Why is this report landing now? Parliament's decay isn't news.

Mimi

Because the cost is compounding. The committee says each year of delay adds about £420m, and weekly maintenance is heading from £1.5m to £2m.

Mark

And the fire warning is the headline.

Mimi

Yes. Outdated electrics are the main fire risk, which is why there are 24-hour fire patrols. Sir Geoffrey asked MPs to picture Notre Dame-style flames on global news.

Luke

That's a rhetorical comparison, though. The report says the risk is real and rising, but I don't see a probability attached to it.

Mimi

Fair. The source gives no likelihood, only the warning and the patrols that already exist.

Mark

What are the choices?

Mimi

A full decant at about £15.6bn over up to 24 years, or a staged decant at about £39.2bn over 38 to 61 years.

Luke

Worth remembering the £40bn and six-decade figure is a recent estimate, and the committee itself calls some of the temporary accommodation costs very high. These numbers could move.

Mark

So what does the committee actually want?

Mimi

A plan to engage MPs within six months, firmer cost estimates, a new select committee, and a timetable pointing to a 2030 decision.

Luke

And no one has said yet which option MPs will pick. That's still unknown.

  • A Commons committee warns that delay has left the Palace of Westminster exposed to a Notre Dame-scale fire, with outdated electrics demanding round-the-clock patrols.
  • Maintenance is already gobbling about £1.5m a week and is racing toward £2m, while every year of inaction adds an estimated £420m to the bill.
  • MPs and peers are boxed in: a 'political allergy' to decisions has stalled a choice between a full decant costing about £15.6bn and a staged decant costing about £39.2bn.
  • The clerks must produce an engagement plan within six months and reshape a tangled governance structure, with a main-project decision targeted for 2030 and the risk of managed decline growing in the meantime.

Beneath the gilded clock tower and the ceremony of Westminster, the building that houses British democracy is quietly aging toward danger. A cross-party committee of MPs has warned that years of hesitation over how to restore the Palace, and how to pay for it, now leave it exposed to a Notre Dame-style catastrophe. The decision that remains unmade belongs to parliamentarians themselves, who must choose between two costly paths and accept that every postponed year makes the bill larger.

A cross-party committee of MPs has issued a stark warning: the Palace of Westminster could suffer a fire on the scale of Notre Dame's, or another catastrophic failure, unless Parliament finally settles how it will pay for and carry out the restoration of its own home. The Commons public accounts committee's report describes years of repeated delay over both the method and the cost of the work.

The Grade I-listed, Unesco-protected building is held together by constant effort. Plumbing fails, roofs leak, masonry crumbles behind scaffolding, and the greatest danger is fire, driven by ageing electrics that already require patrols around the clock. Maintenance costs about £1.5m a week and will soon reach £2m. A recent estimate puts full restoration at up to £40bn over six decades, and the committee says each year of inaction adds roughly £420m.

The chair, Conservative MP Sir Geoffrey Clifton-Brown, spoke of a "political allergy" to making decisions. He asked MPs to imagine flames rising from the roof on global news, with heritage lost and people hurt. Four options have been narrowed to two: a full decant, moving the Commons to Richmond House and the Lords to the QEII centre for about 24 years at roughly £15.6bn, or a staged decant, with the Commons in the Lords chamber for up to two years and a programme lasting 38 to 61 years at about £39.2bn.

The committee is especially uneasy about the temporary accommodation, calling the QEII estimate and the roughly £2bn preparation of the north estate "very high", and noting that Canada built a temporary chamber for far less. It also warns that the programme is bending to fit available space rather than the reverse. It wants simpler governance, a new select committee to scrutinise officials, a clear engagement plan within six months, firmer cost estimates, and a decision on the main project by 2030. A parliamentary spokesperson welcomed the scrutiny and said safety work is already underway, but the choice that MPs have so far avoided is still waiting.

A cross-party committee of MPs has warned that the Palace of Westminster could suffer a fire on the scale of Notre Dame's, or some similarly catastrophic failure, unless Parliament settles how it will pay for and carry out the restoration of its own home. The Commons public accounts committee (PAC) published its report this week. It describes years of repeated delay over how the work should be done and what it will cost.

The building is Grade I-listed and a Unesco world heritage site. Its Victorian fabric is held together by constant maintenance: regular plumbing failures, leaking roofs, and crumbling masonry shielded by a maze of scaffolding. The most serious problem is the persistent risk of fire, mainly from outdated electrics, which requires fire patrols round the clock. Maintenance now costs about £1.5m a week, and the committee says that without action the figure will soon reach £2m.

A recent estimate puts the full restoration at as much as £40bn, with work that could last six decades. The PAC estimates that every year of inaction adds roughly £420m to the programme's cost.

Sir Geoffrey Clifton-Brown, the Conservative MP who chairs the committee, said there has been a "political allergy" to making decisions. He urged MPs to consider the damage to the UK's morale and reputation from a catastrophic failure, and to picture global rolling news footage of flames coming out of the roof, with the heritage destroyed or, worse, people injured or killed. "These are not notional possibilities, but real and rising risks," he said.

The decision belongs to MPs and peers rather than the government. The committee stressed that it is not its role to recommend a particular programme. Four refurbishment proposals, ranging from a nearly full departure from the estate to a version in which only the Lords would move, have been narrowed to two. A "full decant" would move staff to buildings on the north side of the estate, put the Commons in Richmond House, a nearby government building, and send the Lords to the QEII conference centre. It would take up to 24 years and cost about £15.6bn. A "staged decant" would have the Commons move into the Lords chamber for up to two years, and would run for 38 to 61 years at a cost of about £39.2bn.

The report is particularly concerned about the temporary accommodation. It calls the £417m estimate for refurbishing the QEII centre, and a bill of about £2bn to prepare the northern part of the estate for a decant, "very high". It notes that Canada installed a temporary chamber for much less while its parliamentary estate was refurbished. The committee also worries that the programme is being shaped around what temporary space is available, rather than the space being delivered to meet the programme's needs.

On governance, the PAC calls the current arrangements "far too complex" and wants them simplified. It proposes a new restoration and renewal select committee so MPs can hold senior officials to account. Within six months, it says, the clerks of the Commons and the Lords, who are nominally in charge of the process, should set out a plan to engage parliamentarians properly, something the report says has been lacking. It also asks for more robust cost estimates, a timetable leading to a decision on the main project in 2030, and a more urgent approach to finalising temporary accommodation for both chambers.

A parliament spokesperson said the report "provides welcome scrutiny" and acknowledged its conclusion that without action the Palace will, at best, be in a process of managed decline. They said work is already under way across the estate to keep staff and visitors safe. The next markers are the six-month engagement plan and the choice between the two options that MPs have so far put off.

These are not notional possibilities, but real and rising risks.
— Sir Geoffrey Clifton-Brown, chair of the Commons public accounts committee
The report provides welcome scrutiny.
— Parliament spokesperson